No CrossRef data available.
Published online by Cambridge University Press: 15 September 2007
Key past pilot plant developments in steelmaking and continuous casting are reviewed. The enhanced facility at Teesside Technology Centre is outlined. This comprises an EAF which can tap up to 6.9 t, a combined LAF/tank degasser, vertical with bending caster and ingot casting facilities. The equipment and early commissioning during 2006 are described.